Solar System requirement for Interim OC

The request was successful.

Dear Blacktown City Council,

Greetings!!

Could you please advise of any mandatory requirements of Solar system installation on the new building house to get the interim occupational certificate please?

I understand that BASIX may or may not require solar system installation to meet the NCC Basix 7 requirements. However wondering if there are any other such requirements outside BASIX?

Thank you.
Yours faithfully,

KD

Blacktown Council, Blacktown City Council

1 Attachment

Thank you for your email.  We have forwarded it to the appropriate
section(s) within Council. In line with our service standards for
correspondence, you will receive a reply within 10 working days. If your
email was a request for information under the Government Information
(Public Access) Act 2009, you will receive a reply within 20 working
days. 

 

If the matter is urgent, you can contact our Customer service team Monday
to Friday by phoning 02 5300 6000 between 8.30 am and 4.30 pm or by
visiting us at the Civic Centre on Flushcombe Road, Blacktown between 8.30
am and 4.30 pm.

 

 

[1]cid:image001.png@01D7E2DB.7C1ADF10

 

 

This email and any files transmitted with it may be confidential and
contain privileged information. It is intended solely for the use of the
addressee only. If you are not the intended recipient you must not use,
disclose or copy this communication. If you have received this email in
error please delete it and notify the sender. This footnote also confirms
that this email message has been swept for the presence of computer
viruses.

References

Visible links

Natalie Roberts, Blacktown City Council

Good Afternoon

Please be advised there is no requirement for Solar System for a new dwelling except where required by a BASIX Certificate.

Kind Regards

Natalie Roberts
Building Surveyor
9839 5138
0428 801 645
[email address]
PO Box 63 Blacktown NSW 2148
http://www.blacktown.nsw.gov.au/

show quoted sections