This is an HTML version of an attachment to the Freedom of Information request 'Runway 30 Hobart Airport - Environmental Management of Changes to Aircraft Operations#2- FOI 24 -31'.



Doc 7 
FOI 24-43
Environmental Impact Assessment Process for 
Changes to Aircraft Operations 

AA-NOS-ENV-2.100 
Version 4 
Effective 29 November 2012 
Prepared: s47F
 
Environmental Systems Manager 
Endorsed: s47F
 
Manager Strategy and Systems 
Authorised: s47F
 
A/Executive General Manager, Environment 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
Uncontrolled if printed 
© Airservices Australia 2012 
1 of 34 



Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 

Purpose 
The purpose of this National Operating Standard (NOS) is to prescribe an 
environmental impact assessment process (the Assessment) that must be undertaken 
by Airservices, prior to the implementation of changes to aircraft operations.  
The main goals of the Assessment are to: 
  meet Airservices’ Legislative obligations to: 
–  minimise significant environmental impacts resulting from any action, and ensure 
appropriate environmental assessments are undertaken, as required under the 
Environmental Protection and Biodiversity Conservation Act 1999 (EPBC Act) 
–  ensure air traffic management practices are conducted in a manner that  protects 
the environment, as far as is practicable, as required under the Airservices Act 
1995. 
  minimise Airservices business risks by maintaining effective stakeholder 
engagement and sound corporate citizenship in aircraft noise management 
  provide a standardised and rigorous approach to assessing the impacts of changes 
to aircraft operations, as a demonstration of organisational due diligence in 
environmental management. 
The overall outcome of the Assessment will be a defined environmental risk level and 
risk mitigation strategies for the proposed change  which must be either accepted or 
rejected by the ATC manager accountable for the change (such as the Executive 
General Manager, Service Delivery Line Manager or ATC Line Manager) and the 
manager who is implementing this change (e.g. Project Manager). Consequently, it is 
not the role of Environment Group to accept or reject a proposal. The decision 
ultimately rests with the Change Manager, who is informed by the Assessment and the 
resulting risk determination. 

Scope 
The Assessment applies to all proposed changes to Airservices air traffic management 
practices (Proposals) that may involve a change to aircraft operations. 
Proposals include, but are not limited to, the following: 
  A new, or amendment to an existing, instrument approach 
  A new, or amendment to an existing, flight path or air route 
  Re-classification of airspace 
  Change to preferred runways 
  Change in time of day of operation (e.g. amendments to tower hours of operation – 
the time of day that a tower operates may alter the flight path used by aircraft) 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
  A change that allows use of a flight path/airspace by a different type or number of 
aircraft. 
Note: 
A tactical decision of an air traffic controller to alter the track of an individual 
aircraft does not constitute a Proposal. 
Released 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
3 of 34 









Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 

Impact assessment process 
The Assessment is a staged process with defined ‘gates’ that must be passed through 
prior to Proposal implementation. There are three main elements of the Assessment as 
follows: 
  Initial Environmental Screening, Risk Assessment and Planning 
  EPBC Assessment and Referral Process 
  Environmental Business Risk Assessment and Management. 
This section describes key attributes of the above Assessment elements (including the 
basis for each assessment stage, key actions, responsibilities, and outcomes). This 
section should be read with reference to the Overall Assessment Process Flow 
Diagram (Appendix A) although key process flows are also included within the text 
where relevant. Relevant attributes of the Assessment stages are also summarised in 
Appendix B. 
5.1 
Initial environmental screening, risk assessment and planning 
These Assessment stages provide for an initial environmental impact screening by the 
Proponent on behalf of the Change Manager, the formation of the environmental 
change team involved in the change, and a draft risk assessment (to identify changes 
with an unacceptable level of risk and to assist in planning the level of work required in 
later stages). 
Key steps in this stage are further described in the following subsections. 
Refer to Figure 1 for a flow diagram of the Initial Environmental Screening, Risk 
Assessment and Planning Element.  
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
8 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 



Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.1.1.2 
Assessment basis 
Screening must be undertaken for all changes within the scope of this standard and is 
the first step in the Assessment.  
Screening considers a range of pre defined criteria that relate primarily to aircraft flight 
patterns (including location, altitude and communities over-flown). The screening 
criteria is included in Appendix C. As part of the screening an Initial Risk Assessment is 
also conducted. 
If the Screening result is:  
  TRUE for any criteria then further environmental assessment is not required. 
  FALSE for all criteria then further environmental assessments are required as 
documented in this standard.  
Screening is undertaken in ARMS/CIRRIS and the outcome will determine whether the 
change can proceed or if further environmental assessment must be conducted as part 
of the change. 
The Environmental Services branch perform a quality assurance review of findings 
requiring no further environmental assessment, however the change can be 
implemented without this QA review being completed. If, during QA review, the 
assessment is believed to be incorrect, the change should not proceed without 
rescreening. If the change has already been implemented, then the Accountable ATC 
Manager (or delegate) will be informed and will determine if the associated risk level is 
acceptable (or if further assessments and/or changes are required). 
5.1.1.3 
Required Actions 
The Proponent shall: 
  enter the proposal into ARMS5/CIRRIS and the Airservices’ NRFC register 
  undertake the Screening for Environmental Impact (using the environmental impact 
screening criteria – Appendix C) for all proposals in ARMS/CIRRIS  
  once reviewed by the Change Manager, record in the NRFC (and where appropriate 
ARP), the screening result (including whether further Environmental Assessment is 
required). 
The Change Manager shall: 
  review the Screening for Environmental Impact in ARMS/CIRRIS 
  inform Environmental Services (through CIRRIS) of the outcome 
  where required, seek advice from Environmental Services Branch about the 
screening process. 
The Environment Services Branch shall: 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
  for outcomes where no further environmental assessment is required: 
–  conduct a quality assurance review of the Proponent’s determination against the 
Screening criteria (Appendix C) and any known environmental sensitivities 
(without detailed analysis at this stage) 
Released 
–  notify the Change Manager where the screening outcome is not supported. 
                                                 
5 See AA-GUIDE-ARMS-2.000, Environment Assessment process for ATM changes User Guide 
10 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.1.1.4 
Outcomes of Initial ATS change screening stage 
  A screening result as to whether further environmental assessment is required. 
  If no further environmental assessment is required then the change can continue 
without any other assessment defined in this standard. 
  If further environmental assessment is required, then the ‘Environmental 
Assessment and Planning’ stage must be conducted. 
5.1.2 
Environmental assessment planning 
5.1.2.1 
Purpose 
The purpose of the Environmental Assessment Planning stage is to: 
  form the Environmental Change Team who will be involved in the change (and will 
work together throughout further stages of the environmental assessment process) 
  conduct a risk assessment to identify changes with an unacceptable level of risk and 
assist in determining the level of work that needs to be undertaken in environmental 
analysis and environmental risk mitigation 
  plan the remaining assessment activity 
Refer to Figure 1 for a flow diagram of the Environmental Assessment and Planning 
process. 
5.1.2.2 
Assessment Basis  
The Change Manager (or delegate) shall contact Environmental Services branch and 
Community Relations branch to identify representatives to be part of the Environmental 
Change Team which as a minimum shall be comprised of: 
  The Change Manager 
  Representatives from Environmental Services and  
  Representatives from Community Relations. 
The team may also involve other Subject Matter Experts as necessary. 
On formation of the environmental change team, the Proposal, required assessment 
and community engagement will be discussed and planned (including defining and 
assigning key roles, scheduling progress meetings, and setting milestones and 
deliverable dates). Regular meetings should be conducted throughout the Assessment 
to track progress against milestones. 
As part of planning, a draft risk assessment shall be conducted by the team to 
determine if the change constitutes a ‘Class A’ risk which cannot be mitigated and to 
assess the amount of risk mitigation work required for other risks. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
The risk assessment will consider the following key areas: 
 Community Noise Impact 
 Aircraft Emissions 
  Other environmental impacts (including impacts to wildlife species/communities and 
Released 
habitats, and social and heritage considerations). 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
11 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
The risk assessment will be based on high level considerations of known risk factors 
only (e.g. sensitivities described in existing Airport Noise Risk Assessments, fuel use 
thresholds, listed endangered habitats overflown, etc) and will be undertaken in 
accordance with the Environmental Risk Management Standard. Only limited (non 
technical) risk analysis is undertaken at this stage with no detailed environmental 
analysis being undertaken. 
Changes deemed to constitute a Class A risk which cannot be mitigated shall not 
proceed6 and will be diverted from the Assessment process for reconsideration of 
scope. The planned level of environmental analysis and environmental risk mitigation 
should take in to account the risk level of the change. 
Prior to proceeding to further stages of the Assessment, the draft environmental risk 
assessment should be reviewed by the Accountable ATC Manager (or delegate). Risk 
acceptance does not occur at this phase of the Assessment. 
5.1.2.3 
Required Actions 
The Change Manager (or delegate) shall: 
  contact Environment Services Branch7 and Community Relations Branch to 
establish the Environmental Change Team 
  clarify the relevant proposal change details (where known), including proposed flight 
path, estimated flight numbers, deadline for implementation of proposed change 
etc8 
  not proceed with proposals deemed to have a Class ‘A’ Risk which cannot be 
mitigated (unless the change is redesigned and reassessed or authorised by the 
CEO) 
  facilitate review of the draft environmental risk assessment by the Accountable ATC 
Manager 
  ensure the Accountable ATC Manager’s comments are captured within the draft 
environmental risk assessment. 
The Environmental Change Team shall: 
  agree the composition of the environmental change team  
  agree the assessment process (including key roles, progress meeting schedule, 
milestones and deliverable dates) 
  throughout the entire process, adhere to the change schedule and defined 
milestones and advise other parties in the environmental change team well in 
advance if delays to agreed deliverables are likely 
  throughout the entire process, attend planning meetings and participate in the risk 
assessment process 

by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
  agree risk assessment findings. 
Released 
                                                 
6 As per Airservices Risk Management Framework, activities assessed as constituting a Class A risk are not permitted 
(unless otherwise authorised by the CEO in exceptional circumstances). 
7 Through the Assessments and Programs Manager, Environment Group 
8 This reduces undue reliance on assumptions during and the Assessment and ensures appropriate authority for access 
to change information. 
12 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
The Environmental Services Branch shall: 
  lead the initial environmental risk assessment (using the Environmental Risk 
Management Standard) with respect to the key areas of: 
– Community 
Noise 
Impact 
– Emissions 
Impacts 
–  Other environmental impacts (including impacts to wildlife species/communities 
and habitats, and social and heritage considerations) 
  ensure appropriate involvement by the Change Manager, Community Relations and 
Subject Matter Experts in the initial environmental risk assessment 
  enter the draft risk assessment in ARMS/CIRRIS and advise the Change Manager 
of the record 
  update the environmental risk assessment as requested by the Accountable ATC 
Manager or Change Manager. 
The Community Relations Branch shall: 
  participate in the draft environmental risk assessment and planning process to 
provide guidance on Community Noise Impact and Community Engagement 
Planning. 
The Accountable ATC Manager (or delegate) shall: 
  review and provide comment on the Proposal and risk assessment (note that the 
review must be conducted by a Manager with an appropriate level of risk 
acceptance delegation).  Note final risk acceptance does not occur at this stage. 
5.1.2.4 
Outcomes of Environmental Assessment and Planning Stage 
  The formation of an environmental change team for the proposed change 
  A defined assessment management process (including lead roles, timeframes and 
meeting schedule) 
  A completed draft environmental risk assessment and agreed level of change risk 
which has been reviewed by the Accountable ATC Manager (or delegate) 
  Progression to further assessment stages (i.e. EPBC Assessment and Community 
Engagement Planning and Environmental Analysis). 
5.2 
EPBC assessment and referral process 
Under the EPBC Act, actions that have, or are likely to have, a significant impact on a 
matter of national environmental significance (NES) require approval from the 
Australian Government Minister for Sustainability, Environment, Water, Population and 
Communities (the Environment Minister).  
In addition to the above, Section 160 of the EPBC Act, requires Commonwealth 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
agencies (such as Airservices) to seek the Environment Minister's advice9  for the 
adoption or implementation of a plan for aviation airspace management involving 
aircraft operations that have, will have, or are likely to have a significant impact on the 
environment in general (i.e. not just impacts to matters of NES). 
Released 
                                                 
9 Under the EPBC Act, advice is sought through the preparation of an EPBC Referral. 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
13 of 34 



Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.1 
Internal EPBC assessment for potential significance 
5.2.1.1 
Purpose 
This assessment stage determines whether the change has the potential to cause 
significant impact to the environment, and if it therefore warrants advice from the 
Environment Minister through a referral process in accordance with the EPBC Act. 
5.2.1.2 
Basis of the assessment 
The internal EPBC impact assessment will be undertaken by the Environmental 
Services Branch who will assess the change based on defined assessment criteria.  
For all changes, the internal EPBC assessment criteria for potential significance shall 
be endorsed by the EGM Environment prior to commencement of the assessment. 
Airservices internal EPBC assessment criteria shall: 
  define standardised significant impact measures and thresholds which, if reached, 
result in a finding of ‘potentially significant’10. Use of standardised measures and 
thresholds shall minimise the potential for subjectivity within the EPBC assessment 
process; 
  considers noise impacts on communities as well as impacts to a range of 
environmental values and is aligned with the ‘Actions on, or impacting upon, 
Commonwealth land, and actions by Commonwealth Agencies, Significant Impact 
Guideline 1.2’ (Commonwealth of Australia 2010). 
A Proposal must be redesigned, or referred for assessment under the EPBC Act, any 
change assessed as having ‘potential significant impact’. 
5.2.1.3 
Required Actions 
The Change Manager (or delegate) shall: 
  Provide all relevant Proposal details (including flight paths, flight frequencies, flight 
numbers, aircraft types etc), required to make the assessment, in accordance with 
agreed project timelines 
  accept that when a decision of ‘potential significant impact’ is reached, then the 
Proposal cannot proceed as planned without being referred to the Environment 
Minister 
  in consultation with the Accountable ATC Manager, make a decision on whether to 
proceed with the Proposal as planned, or whether to redesign and reassess the 
Proposal (based on the Assessment findings). 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
                                                 
10 Note that the assessment should rarely result in a finding of ‘significant impact’ as it is Airservices position that this is a 
determination that only the Federal Environment Minister can make through advice sought by Airservices and following 
formal assessment under the EPBC Act. Further, the reversible nature of Aircraft operations is not consistent with the 
notion of ‘significant impact’. 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
15 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
The Environmental Services Branch shall: 
  define the EPBC significance criteria and assessment methodology for the change 
and seek endorsement of the approach from the Executive General Manager 
Environment 
  provide the Environment Change Team with an indicative program for completion of 
necessary environmental assessments 
  undertake and manage the Assessment, and make a recommendation with respect 
to potential significance, using the predefined EPBC significance criteria and 
assessment methodology 
  produce a report that documents the assessment and findings 
  enter the outcomes of the assessment in ARMS/CIRRIS. 
The Executive General Manager Environment shall: 
  endorse the EPBC significance criteria and assessment methodology for the change 
  accept or reject any finding regarding potential environmental significance. 
5.2.1.4 
Outcomes 
  A decision on whether or not the Proposal is likely to result in ‘potential significant 
impact’ environmental impacts if implemented as planned 
  If the Proposal is deemed NOT to constitute ‘potential significant impact’: 
–  Continuation of the Environmental Business Risk Assessment and Management 
stages (informed by the EPBC Assessment result). 
  If the Proposal is deemed ‘potentially significant’ by Airservices: 
–  A decision from the Change Manager (in consultation with the Accountable ATC 
Manager) on whether to proceed with the Proposal as planned (i.e. whether to 
submit a referral under the EPBC Act) 
–  Progression to the EPBC Referral and Assessment stage if the Proponent 
decides to proceed with the Proposal as planned. 
5.2.2 
EPBC referral and assessment under the EPBC Act 
5.2.2.1 
Purpose 
The purpose of this stage is to seek advice (through a referral) from the Minister 
regarding whether a Proposal constitutes ‘significant impact’ under the EPBC Act, and 
if so, to have the Proposal formally assessed. 
This is required for all Proposals which have met the criteria for ‘potential significant 
impact’ under the Assessment, and where the Proponent has decided to proceed with 
the Proposal as planned. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
5.2.2.2 
Assessment basis 
Proposals determined to have ‘potential significant impact’ are ‘referred’ to the 
Environment Minister for advice as to whether the Proposal warrants formal 
assessment under the EPBC Act. This is known as an ‘EPBC Referral’.  
Released 
EPBC Referrals must describe the Proposal (including Proposal details, existing 
environment and potential impacts) and are required to be submitted in the approved 
form (a template is provided on the SEWPaC website). The Environment Minister must 
assess the referral and provide advice within 20 business days. 
16 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
Following assessment of a referral, the Minister can make one of three decisions as 
follows: 
  Controlled action – Action is subject to the assessment and approval process 
under the EPBC Act, as the Proposal is deemed likely to cause significant impact 
  Not controlled action (‘particular manner’) - approval is not required if the action 
is taken in accordance with the manner specified 
  Not controlled action – Approval is not required if the action is taken in accordance 
with the Referral. 
If the Minister decides that the Proposal is likely to result in ‘significant impact’ to the 
Environment (i.e. it constitutes a ‘controlled action’) then formal assessment under the 
EPBC Act is required. Formal assessment may be undertaken under a range of 
processes defined in the EPBC Act (as directed by the Minister) which are not 
described in this document. 
5.2.2.3 
Required Actions 
The Environmental Change Team shall: 
  attend regular Proposal meetings and Proposal definition activities as required 
(including workshops and meetings with external government departments) 
  review all required information, draft reports and correspondence, and provide any 
required feedback in accordance with agreed project timelines. 
The Change Manager (or delegate) shall: 
  provide all relevant Proposal details (including flight paths, flight frequencies, flight 
numbers, aircraft types etc), required to prepare required assessment 
documentation, in a timely manner on behalf of the Proponent. 
Environmental Services shall: 
  prepare, or manage preparation of, an EPBC Referral on behalf of the Change 
Manager 
  prepare, or manage preparation of, any environmental analysis documentation 
required to support formal assessment under the EPBC Act (if required) 
  manage any EPBC referral and assessment processes 
  enter the outcomes of the assessment in ARMS/CIRRIS. 
The Executive General Manager Environment shall: 
  endorse and provide the EPBC Referral to the Environment Minister. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
17 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.2.4 
Outcomes 
  A request for advice (i.e. an EPBC Referral) sent to the Minister by the Executive 
General Manager Environment, regarding whether or not the Proposal is likely to 
result in ‘significant impact’ 
  Advice and/or a decision from the Environment Minister regarding whether the 
Proposal constitutes ‘significant impact’ and any further assessments or actions 
required under the EPBC Act (following referral of any Proposal to the Minister for 
assessment) 
  If the Proposal is deemed by the Environment Minister (following referral) as likely to 
have a ‘significant impact’ (i.e. constitutes a ‘controlled action’): 
–  An environmental assessment report (in whichever form specified) sent to the 
Environment Minister, for formal assessment under the EPBC Act. 
–  A decision from the Minister, following review of the environmental assessment 
report, regarding whether to approve the action, and what conditions (if any) to 
impose. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
18 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.3 
Environmental Business Risk Assessment and Management 
These Assessment stages provide for identification, assessment and management of 
environmental business risks to Airservices resulting from implementation of a 
Proposal. Environment business risks are those that may not trigger Airservices EPBC 
Assessment criteria, but may still represent environmental, financial and reputational 
business risks for Airservices.  
The Environmental Business Risk Assessment provides an additional tier of impact 
assessment, which complementary to regulatory requirements and further 
demonstrates due diligence in environmental management.  
These Assessment stages incorporate environmental analysis of noise impacts, risk 
analysis, and development of a Community Engagement Plan.   
Key steps in this Assessment stage are further outlined below. While activities are 
identified in a staged order, they are necessarily inter-related and iterative in nature. 
Refer to Figure 3 for a flow diagram of the Environmental Business Risk Assessment 
and Management Stages. 
Accountable ATC Manager (or 
delegate) review of Initial Environmental 
Risk Assessment
No EPBC Impact / 
Community 
Environmental 
Assessment Result
Engagement Planning
Analysis
Informs any 
Referral
Risk Management and 
EPBC Referral
Risk not accepted 
Community Engagement 
Result
by Accountable ATC Manager
Plan Implementation
Do not implement change, 
reassess scope or identify 
new mitigation
Environmental Pre-
Risk not accepted 
Implementation Review
by Accountable ATC Manager
Change Implementation
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Post Implementation 
Review
Released 
 
Figure 3: Flow Diagram of Environmental Business Risk Assessment and 
Management Process 

 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
19 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.4 
Community Engagement Planning 
5.2.4.1 
Purpose 
The purpose of this stage is to: 
  inform the level of, and guide the approach to, further environmental impact 
analyses and change design 
  commence development of the Community Engagement Plan (CEP) which is a 
significant mitigator for community noise impact. 
5.2.4.2 
Content and approach 
Community Engagement Planning will commence following the definition of change 
environmental risks (following the draft Environmental Risk Assessment, described in 
Section 5.1). It is an iterative process that will continue through subsequent stages of 
environmental analysis and risk assessment. Although drafting may commence, the 
CEP will only be finalised on completion of all Stages of the Environmental Business 
Risk Assessment (and prior to change implementation).  
The CEP guides engagement and consultation with the community in line with 
Airservices Communication and Consultation Protocol.  The CEP will also document 
the process for the Post Implementation Review (PIR) of the environmental impact of 
the change. 
Following the initial Environmental Risk Assessment, and based on the identified risk 
levels, the level of required community engagement and consultation will be 
determined. For example, more in depth community engagement will be necessary for 
identified community noise impacts with a class B risk, than for those with a class C or 
D risk.   
The required environmental analyses to support this community engagement will also 
be based upon the necessary level of community engagement. For example, more 
detailed noise impact analyses will be recommended for identified community noise 
impacts with a class B risk, than for those with a class C or D.  
The recommended level of community engagement, and environmental analyses to 
support the planning, will be discussed and agreed with the Environmental Change 
Team, prior to Community Relations and Environmental Services developing the 
associated plans and conducting the analyses. 
5.2.4.3 
Required Actions 
The Environment Change Team shall: 
  agree the recommendations of the Community Engagement Planning stage. 
The Change Manager (or delegate): 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
  Review and provide comment on the draft and final version of the CEP; 
  Accept the recommendations of the Communication and Engagement Planning 
stage. 
Environment Services shall: 
Released 
  agree the level of further noise impact analysis to be undertaken to support 
preparation of the CEP. 
20 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
Community Relations shall: 
  manage the community engagement planning phase 
  recommend the level of Community Noise Impact Analysis to be undertaken to 
support preparation of the CEP 
  ensure appropriate involvement (and where necessary signoff) from subject matter 
experts (including Government and Industry Affairs) and alignment with other 
stakeholder engagement plans. 
5.2.4.4 
Outcomes 
  Commencement of drafting of the CEP 
  A defined focus and level of Community Noise Impact Analyses to be undertaken to 
support preparation of the CEP 
  An agreed level and focus of community engagement and consultation (as 
documented in the CEP). 
5.2.5 
Environmental Analysis  
5.2.5.1 
Purpose 
The purpose of this stage is to identify and analyse potential environmental, financial 
and reputational business impacts and benefits of the change.   
5.2.5.2 
Assessment Basis  
The Environmental Analysis stage provides additional information about the proposed 
change with respect to the three key areas of potential environmental impacts (and 
benefit) as follows: 
 Community Noise Impact 
 Emissions 
  Other environmental issues (including impacts to wildlife species/communities and 
habitats, and social and heritage considerations). 
There must be an agreement within the Environmental Change Team on the purpose 
for conducting individual analyses. These may include: 
  to support refinement or optimisation of the design (including alignment with, and 
incorporation of EBD principles wherever possible) 
  to support community engagement and consultation planning  
  to define potential noise or emissions benefits 
  to support an EPBC Referral (after a potential need for referral has been identified 
through the EPBC Assessment Process ) 
  to assist in communication or engagement with other stakeholders (e.g. Industry) 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Environmental Services will lead the analyses where appropriate but will work closely 
with the Environmental Change Team throughout the process. 
The level and focus of analyses will be determined by the drivers for conducting the 
analysis.  For example, electoral boundary analysis may be conducted to support 
Released 
stakeholder engagement planning where risks associated with particular demographics 
or interest groups have been identified. 
Any analysis conducted will also assist in review and update of the Environmental 
Business Risk Assessment. 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
21 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.5.3 
Required Actions 
The Environmental Change Team shall: 
  agree the level, focus and schedule of impact analyses 
  agree the resulting risk level. 
The Change Manager (or delegate) shall: 
  provide all relevant Proposal details (including flight paths, flight frequencies, flight 
numbers, aircraft types etc), required to make the assessment, in a timely manner  
Community Relations shall: 
  define what analysis is required to assist with the community engagement and 
consultation planning. 
Environmental Services Branch shall: 
  analyse the impact using the agreed methodology and metrics 
  manage the impact analysis process (including holding meetings, managing 
deadlines and milestones) 
  produce a report that documents the impact analysis and results 
  ensure appropriate involvement by the Change Manager, Community Relations and 
Subject Matter Experts in the update of the environmental risk assessment 
  enter the updated risk assessment in ARMS/CIRRIS and advise the Change 
Manager of the record. 
5.2.5.4 
Outcomes 
  Documented impact analyses for the Proposal that where necessary address: 
– Community 
Noise 
Impact 
– Emissions 
–  Other environmental impacts (including impacts to wildlife species and habitats, 
and social and heritage considerations). 
  Results of the analyses to assist further design work, development of a CEP, 
understanding of environmental benefits, preparation of an EPBC Referral and/or 
other stakeholder engagement. 
  Progression to the Risk Management and CEP Implementation Stages 
5.2.6 
Risk Management and CEP Implementation  
5.2.6.1 
Purpose 
The purpose of the Risk Management and CEP Implementation stage is to: 
  update, review and accept the level of change risks (resulting from the 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Environmental Analysis and Community Engagement Planning stage) 
  implement the CEP 
  update review and accept risks following implementation of the CEP to determine 
whether to implement the Proposal. 
Released 
22 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.6.2 
Process description 
Risk review and acceptance 
Following environmental analysis and communication planning, the environmental 
business risks are updated (by Environmental Services Branch) and need to be 
reviewed and accepted (or rejected) by the Accountable ATC Manager (or delegate). 
Risk review at this stage will also consider any Ministerial advice or assessment 
findings following any EPBC Referral or assessment processes undertaken in 
accordance with the EPBC Act (as described in Section 5.2.2).  
Upon risk acceptance, the proposal can proceed to the CEP implementation stage.  If 
the risk is not accepted the proposal must be redesigned or not pursued further. Risk 
acceptance recorded in ARMS/CIRRIS  
Following implementation of the CEP, a further risk review and update is undertaken 
based on the findings of the community engagement and consultation process.  This 
process captures the feedback received from the community and ensures that the risk 
assessment reflects this information. On acceptance of the resulting risk, the Proposal 
can be implemented (if not accepted it must be redesigned). 
CEP Implementation  
The CEP is implemented in accordance with the methodology it describes. 
Implementation methodology will vary for each CEP (targeted to the particular 
Proposal) but is likely to include: 
  a presentation to relevant community groups and bodies (e.g. Airport Community 
Aviation Consultation Groups – CACGs) where the proposed change is 
communicated, (including timeframes for implementation, flight paths, and likely 
noise levels/associated impacts) 
  publication on the Airservices website 
  participation in other activities required by other stakeholder engagement plans (e.g. 
Communication to politicians) where necessary 
  a request for comments on the intended Proposal to be provided by a specified 
date. 
5.2.6.3 
Required Actions 
The Environment Change Team shall: 
  agree the updated risk level (pre and post CEP implementation) 
  collaborate to implement the CEP as required 
  discuss outcomes of the CEP implementation (and consultation process) and agree 
any required changes to risk assessments and/or Change design 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
  agree any further environmental actions that must undertaken taken as follows: 
–  prior to implementation of the Proposal (if final risk accepted) 
–  with respect to redesign or re-assessment (if final risk is not accepted)   
Released 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
23 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
The Change Manager shall: 
  facilitate review of the updated environmental risk assessment by the Accountable 
ATC Manager (or delegate) 
  not proceed with proposals deemed to have a Class ‘A’ Risk which cannot be 
mitigated (unless the change is redesigned and reassessed or authorised by the 
CEO) 
  ensure the Accountable ATC Manager’s (or delegate’s) comments are captured with 
respect to the risk review and associated decisions. 
The Accountable ATC Manager (or delegate) shall: 
  review (i.e. accept or reject) and provide comment on the risk assessment findings 
(note that the review must be conducted by a Manager with an appropriate level of 
risk acceptance delegation) 
  risk review shall be undertaken at the following stages: 
–  after the Environmental Analysis/Community Engagement Planning stages and 
risk update and  
–  following implementation of the CEP and any risk update required after the 
consultation process. 
Environmental Services shall: 
  update the Proposal risk level following the Environmental Analysis and Community 
Engagement Planning Stages 
  participate in implementation of the CEP (as Subject Matters Experts) as required 
and as agreed by the Environmental Change Team 
  update the Proposal risk level again following implementation of the CEP (and 
based on consultation findings and agreement within the Environment Change 
Team) and advise the Change Manager of the record 
  ensure appropriate involvement by the Change Manager, Community Relations and 
Subject Matter Experts in the environmental risk assessment 
  update the environmental risk assessment as requested by the Accountable ATC 
Manager or Change Manager. 
Community Relations shall: 
  lead the environmental risk review and update (pre and post CEP implementation), 
in collaboration with Environmental Services Branch 
  lead and manage implementation and delivery of the CEP (including all consultation 
and delivery at relevant forums - including CACGs and Community groups) 
  compile all feedback and consultation records and communicate the findings to the 
Environmental Change Team 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
24 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.6.4 
Outcomes  
  A revised risk assessment and agreed level of Proposal risk (either Class A, B, C, or 
D) to guide implementation of the CEP 
  Implementation of the CEP to relevant stakeholders (including relevant CACGs, 
other Community groups as required) 
  A revised risk assessment and agreed level of Proposal risk (either Class A, B, C, or 
D) post implementation of the CEP 
  Ultimately a decision on whether or not to proceed with implementing the Proposal 
(on final risk assessment) or whether redesign is necessary. 
5.2.7 
Environmental Pre-Implementation Review 
5.2.7.1 
Purpose 
The purpose of this review is to verify that the Proposal has undergone the appropriate 
environmental assessment and risk management processes prior to implementation  
It provides a final ‘gate’ to the Assessment to ensure compliance with this Standard 
and the Airservices EMS. 
5.2.7.2 
Required Actions 
The Change Manager shall: 
  conduct a pre-implementation review prior to implementing any Proposal to verify 
that the following has been undertaken: 
–  An Internal EPBC Assessment has been conducted 
–  Any requirements based upon the Environment Minister’s response to an EPBC 
Referral have been met 
–  The CEP has been conducted and the feedback captured within the 
Environmental Business Risk Assessment 
–  The final environmental risk assessment of the change has been accepted 
–  The result has been recorded in ARMS/CIRRIS (and NRFC and ACP if required). 
  advise the Accountable ATC Manager of the risk acceptance status following the 
Pre-Implementation review 
  not implement the Proposal until final risk acceptance has been undertaken and 
recorded in ARMS/CIRRIS. 
5.2.7.3 
Outcomes 
Verification by the Change Manager that the change is acceptable for implementation 
from an Environmental perspective. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
25 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
5.2.8 
Environmental Post Implementation Review 
5.2.8.1 
Purpose 
The purpose of the PIR is to assess implementation of the Proposal with respect to 
environmental management performance against associated commitments (as 
described in the CEP and any other Proposal documentation).  The Environmental PIR 
shall focus on Community Noise Impact.  Should other Environmental Post 
Implementation Review be required (e.g. emissions impact), this should be planned 
separately by the environmental change team. 
5.2.8.2 
Assessment Basis  
Following implementation of a Proposal, Community Relations will lead the PIR in 
accordance with principles described in the Standard Project Management 
Methodology. 
Where appropriate the PIR should include an assessment of actual noise levels 
received at ground level and analysis of community response (i.e. complaints). 
A PIR report shall be provided to the Accountable ATC Manager and Change Manager 
for acceptance.  It shall also be provided to the Environment Change Team and other 
relevant external parties as documented within the CEP. 
5.2.8.3 
Required Actions 
The Environment Change Team shall: 
  agree the schedule for the PIR 
  identify and plan separate PIR as necessary for environmental factors other than 
community noise impact. 
Community Relations shall: 
  document the plan for PIR within the CEP 
  conduct a PIR in accordance with the CEP 
  provide the PIR report to the Accountable ATC Manager and Change Manager for 
acceptance 
  provide the PIR report to the Environment Change Team 
  provide the PIR report to external parties as documented within the CEP. 
5.2.8.4 
Outcomes  
  Confirmation as to whether the actual outcomes of the change met the predicted 
outcomes 
  Identification of process improvements. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
26 of 34 
Version 4: Effective 29 November 2012 
AA-NOS-ENV-2.100 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 

References/related documents 
6.1 
Internal documentation 
  Environment Policy - C-POL:AA 000 6 
  Environmental Risk Management National Operating Standard  
  Airservices Communication and Consultation Protocol - 
http://www.airservicesaustralia.com/wp-content/uploads/Communication-and-
Consultation-Protocol WEB.pdf  
6.2 
External documentation 
  SEWPaC 2010, ‘Actions on, or impacting upon, Commonwealth land, and actions by 
Commonwealth agencies’  Significant impact guideline 1.2, Environment Protection 
and Biodiversity Conservation Act 1999. 
  AS2021-2000:  Acoustics-Aircraft noise intrusion-Building siting and Construction, , 
Standards Australia International Ltd, Sydney, NSW 2001 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
Released 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
27 of 34 











Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
Appendix C 
Initial ATS Screening Criteria 
If the Screening result is:  
  TRUE for any of the below criteria, then further environmental assessment is not 
required;  
  FALSE for all the below criteria, then further environmental assessments are 
required as documented in this standard.  
Criteria 1 
The proposal does not have the potential to affect aircraft movements in a manner that 
may create or enable: 
  an increase in number of aircraft operations 
  a decrease in aircraft altitude 
  a change in aircraft lateral location 
  a change in aircraft type 
  a change in time of aircraft operations 
  an increase in kilometres flown 
  the generation of public concern 
Criteria 2 
The proposal relates to a section of a flight path that is: 
  above 20 000 FT AGL and 
–  does not pass over a population centre (i.e. community, town, or city) and 
–  is not associated with a particularly sensitive environment (e.g. National Park, or 
Sydney) and 
–  is not associated with supersonic aircraft 
or 
  above the ocean and 
–  is greater than 5 NM off shore and 
–  is not associated with a particularly sensitive environment (e.g. National Park, or 
Sydney region) 
–  is not associated with supersonic aircraft 
Criteria 3 
The proposal relates to a GPS and/or instrument approach proposal in small remote 
communities where: 
  all populated areas are outside the tolerances of the approach and missed 
approach; or the populated areas are already exposed to same aircraft noise. i.e. 
by Airservices Australia pursuant to the Freedom of Information Act 1982 (Cth)
the approach/missed approach coincides with current VFR or IFR paths and 
  the airport is remote from major training airports such that no increase in training 
traffic may be expected and 
  aircraft in use are piston engine, turbo props and Bizjets (light corporate jet) only 
Released 
and 
  the airport is in a designated remote area on (for central and northern Australia) 
shown in ERSA. 
AA-NOS-ENV-2.100 
Version 4: Effective 29 November 2012 
33 of 34 

Doc 7 
FOI 24-43
Environmental Impact Assessment Process for Changes to Aircraft Operations 
Appendix D 
Other Commercial Revenue – explanatory notes 
Other Commercial Revenue (OCR), otherwise referred to as ‘Unregulated Revenue’ or 
Non-Airways Revenue, relates to the provision of goods or services other than those 
which are provided as part of the regulated service that is subject to the Long Term 
Pricing Agreement (LTPA) with customers. For the avoidance of any doubt, OCR is a 
term applied to account for those activities not funded through airways revenue. 
Airservices OCR includes (but is not limited to): 
  provision of charting services and other publications 
  maintenance or provision of navaids under contract 
  provision of air traffic services under contract (e.g. for Solomon Islands and Nauru) 
  delivery of training and  
  funds we receive for official development assistance (aid) activities. 
For further information on OCR, refer to the following documents: 